Mechanic's Liens & Payment Bonds

Construction runs on credit: suppliers deliver materials and subcontractors work before they are paid. A mechanic's lien and payment bonds are legal tools to protect that payment. Both sides, contractors and property owners, need to understand how they work.

What is a mechanic's lien?

A lien is a legal claim against a property for unpaid work or materials that improved it. If it is not resolved, it can lead to foreclosure and sale of the property. In many states, subcontractors and suppliers can place a lien even if the owner paid the general contractor.

Who can file

Typical steps for a claimant

  1. Preliminary notice: early in the job, many states require subs and suppliers to send notice to the owner and general contractor to keep lien rights.
  2. Record the lien in the county records within the deadline after the last work, often 60 to 120 days or more.
  3. Serve notice to the owner as required.
  4. Sue to enforce the lien within a short period, often within months to a year or so.

For property owners

Payment bonds on public projects

Warning: Deadlines are short and strict. If you are owed money on a job, see a construction attorney or your local contractor association soon after the problem starts.