Scaffold Ties, Guying & Bracing

A tall scaffold is like a thin tower. Without ties to the building and proper bracing it can sway, rack and tip over, even without much load. Ties and braces are structural parts, not optional extras, and collapses often follow the removal of ties for convenience.

The 4-to-1 rule

OSHA (29 CFR 1926.451(c)(1)) says supported scaffolds with a height-to-base-width ratio of more than 4 to 1 must be restrained from tipping by guying, tying, bracing or equivalent means. For example, a scaffold with a base 5 feet wide needs restraint above 20 feet of height. Where you measure the base width (the outside dimension of the posts, including outriggers if they are properly built and used) matters. Follow the design.

Types of restraint

MethodWhat it doesNotes
Wall ties (rigid ties)Tubes or couplers connecting the scaffold to the building structureResist pulling in and pushing out. Best where the wall is sound
Through ties and reveal tiesTie through a window opening or pressed in a revealMust use the right tubes and not rely on window frames; check the structure
Anchor tiesEyebolts or masonry anchors in the wall with a tube or wirePull-test anchors; use anchors rated for the substrate
Guy wires or ropesCables from the scaffold to ground anchors or structureOnly where designed. Must resist tipping loads, not just hold tension by hand
Outriggers and counterweightsExtend the base so the scaffold resists tippingMust be designed and used as the manufacturer says; ballast only if engineered

Bracing

Common ties mistakes

Wind and sheeting

Competent person duties

Scaffold ties checklist