Management of Change (MOC)

Many industrial disasters start with a change nobody thought through: a different valve, a bypassed alarm, a substituted chemical, a shortcut in a procedure or a smaller crew. Management of change (MOC) is a formal way to ask “what could go wrong because of this change?” before it's made, and to make sure everyone affected knows.

What counts as a change

A “replacement in kind” (an identical part for the same design) usually doesn't need MOC, but anything different in design, material or specification does. When in doubt, ask. See Process Safety Management.

The OSHA requirement

For facilities covered by OSHA's Process Safety Management standard (29 CFR 1910.119), employers must establish and implement written procedures to manage changes to process chemicals, technology, equipment and procedures (except replacements in kind), and changes to facilities that affect a covered process. The procedures must address:

Employees involved in the process and maintenance and contract employees whose job tasks are affected must be informed of and trained in the change before start-up, and the process safety information and operating procedures must be updated. Facilities not covered by PSM benefit from the same approach. See HAZWOPER and Ammonia Refrigeration.

Typical MOC steps

  1. Request: describe the change, why it's needed and where, on a form or in the MOC system.
  2. Screen: decide if it's a real change or a replacement in kind, and whether it's temporary or permanent.
  3. Review the hazards: a team including operations, maintenance, engineering and safety asks what could go wrong, using a hazard review method such as a what-if or a hazard and operability study. See Maintenance Technicians.
  4. Approve: get sign-off from the right people, with conditions.
  5. Prepare: update drawings, procedures and safety information, order the right parts, and plan training.
  6. Train and inform everyone affected, including contractors and other shifts. See Shift Handovers.
  7. Pre-startup safety review: check that the change was built as designed, procedures are in place, and training is done before startup. PSM requires this for new facilities and modified ones where the change affects the process safety information.
  8. Close out: update records and confirm the change worked as planned.

Temporary changes and emergencies

Workers' role

MOC checklist

Standards & references