Timber Shoring

Timber shoring uses wood posts and braces to hold up the sides of a trench so the walls can’t collapse on workers. It was the first trench protection and is still used for small jobs, odd-shaped excavations and places where trench boxes won’t fit. Timber shoring only works if it’s designed, built and inspected correctly.

Why shoring is used

Parts of a timber shoring system

PartWhat it does
Uprights (vertical members)Planks or posts placed against the trench wall. They carry the load of the soil
Wales (horizontal members)Beams that run along the trench and hold the uprights against the wall
Cross braces (struts)Horizontal members that span the trench and press the wales and uprights against the walls. Wood cross braces are usually wedged or secured so they can’t slip
Spreaders or screw jacksAdjustable braces that tighten against the wales. Timber or hydraulic jacks are used with timber systems
Sheeting or laggingBoards between uprights that hold soil that would otherwise squeeze through gaps

Systems may be spot (intermittent) bracing, where uprights are spaced apart, or continuous sheeting, where boards form a solid wall. Looser or wetter soil needs tighter spacing.

OSHA’s timber shoring tables

Materials

Installing timber shoring

  1. Plan first. A competent person classifies the soil, picks the system and checks for utilities, water, surcharge loads and nearby structures. See Surcharge Loads, Call 811 and Excavations Near Structures.
  2. Dig carefully in stages. Install shoring as the trench is dug, not after it is already deep. Don’t let anyone enter a trench until protection is in.
  3. Set uprights against the wall and drive them down as digging proceeds, keeping them at the spacing in the table.
  4. Install wales across the uprights at the specified heights, and install cross braces tightly between wales, level and square to the trench.
  5. Secure the braces so they can’t drop or kick out. Use wedges, cleats or jacks. Make sure the braces are tight against the wales.
  6. Install from the top down. Install the first bracing at the top, and keep going down as the trench deepens.
  7. Provide ladders or ramps within 25 feet of workers in trenches 4 feet or deeper. See Access, Egress & Spoils.
  8. Keep spoil piles and equipment at least 2 feet back from the edge. See Barriers & Fall Protection at Excavation Edges.

Removing shoring

Inspection and daily duties

Common mistakes

Timber shoring checklist

Standards & references